PROBLEM TO BE SOLVED: To provide a building method for a house that enables the house to be built in a short period of time.SOLUTION: Steps for building a first floor part of a house includes a manufacturing step S11, a transport step, an installation step S13, and a curing step S14. In the transport step, a plurality of first floor panels manufactured in the manufacturing step S11 is transported sequentially from a manufacturing site to a construction site, when a prescribed initial strength has been demonstrated. In the installation step S13, the plurality of first floor panels transported is installed sequentially on a foundation at the construction site. In the curing step S14, the plurality of first floor panels installed in the installation step S13 is cured on the foundation until a prescribed target strength is demonstrated. In a step for building a second floor part also, curing is performed in a same way at the construction site.SELECTED DRAWING: Figure 2 |