发明名称 LONG-SIZED MEMBER BURYING OR DRIVING METHOD
摘要 PROBLEM TO BE SOLVED: To perform rapid and smooth foundation work at a low cost and to prevent worsening of work environment and worsening of environment around a construction site. SOLUTION: Prior to burying work, a place to bury a pile in is excavated by an auger 2 to provide a hole 1a. In this case, bubbles comprising a foaming solution 14 and air are mixed in excavated earth 13 excavated by the auger 2, and agitated. The excavated earth 13 thereby has fluidity to facilitate discharge. The excavated earth 13 discharged onto the ground surface is rapidly returned into its original property by a defoaming agent. The volume ratio of air to the foaming solution contained in the bubbles is set to about(5-30)to 1.
申请公布号 JP2000336648(A) 申请公布日期 2000.12.05
申请号 JP19990152879 申请日期 1999.05.31
申请人 TACHIBANA MATERIAL CO LTD 发明人 ISHII SABURO
分类号 E02D7/00;(IPC1-7):E02D7/00 主分类号 E02D7/00