发明名称 Systems and methods for collaborative construction planning
摘要 Systems and methods for collaborative construction planning are provided herein. An example method includes establishing a milestone or completion event for a construction project plan, assembling the construction project plan by defining activities for the milestone or completion event. Each of the activities is associated with a team member which accomplishes a given activity, and arranging the activities in reverse chronological order starting with the milestone or completion event, according to an order of dependency of execution of activities. The method also includes displaying the construction project plan in such a way that the activities are illustrated to show the order of dependency between activities.
申请公布号 US9406039(B2) 申请公布日期 2016.08.02
申请号 US201414207312 申请日期 2014.03.12
申请人 Autodesk, Inc. 发明人 Reed Dean;Khanzode Atul;Davison Michael;Elkins Todd;Singhania Vishal
分类号 G06Q10/00;G06Q10/06;G06Q50/08 主分类号 G06Q10/00
代理机构 Fish & Richardson P.C. 代理人 Fish & Richardson P.C.
主权项 1. A method for providing a collaborative construction project plan using a collaborative planning system, the method comprising: establishing a milestone or completion event for a construction project plan; assembling the construction project plan by: defining activities for the milestone or completion event, wherein each of the activities is associated with a team member which accomplishes a given activity; andarranging the activities in reverse chronological order starting with the milestone or completion event, according to an order of dependency of execution of activities; displaying the construction project plan in such a way that the activities are illustrated to show the order of dependency between activities; generating, on a graphics display, a visualization of a critical path for the construction project plan; identifying, on the graphics display, critical activities associated with the critical path by highlighting the critical path activities with a visual indication, in the visualization, that shows a path of necessary activities in the construction project plan; receiving first user input to the visualization indicating a modification to an activity; in response to the receiving the first input, calculating time data of the construction project plan; interactively and in response to the first input, updating the visualization to displaying the calculated time data of the construction project plan on the graphics display to show changes in the critical path such that further user input continues to interactively update the visualization; displaying, on the graphics display, an interactive two-dimensional floor plan view, the interactive two-dimensional floor plan view displaying an interactive building map that includes activities as located in a building space; receiving second user input indicating a user preference for three-dimensional view; and in response to receiving the second input, switching, on the graphics display, the interactive two-dimensional floor plan view into a three-dimensional floor plan view.
地址 San Rafael CA US