摘要 |
PROBLEM TO BE SOLVED: To provide an economical and high-quality concrete structure construction method or the like.SOLUTION: An outer peripheral section 11 of a concrete structure 1 is constructed by placing concrete with dense arrangement of main reinforcement 111. Then, the concrete structure 1 is constructed by placing the concrete in an inner section 12 inside the outer peripheral section 11. The concrete for the outer peripheral section 11 develops high strength after the same is cured and has a large slump value. The concrete for the inner section 12 develops lower strength than the concrete for the outer peripheral section 11 after the same is cured and has a lower slump value than the concrete for the outer peripheral section 11.SELECTED DRAWING: Figure 3 |