发明名称 |
CONSTRUCTION METHOD FOR UNDERGROUND WIDENED PART |
摘要 |
PROBLEM TO BE SOLVED: To provide a construction method for an underground widened part that may be implemented safely without excavation.SOLUTION: A construction method for an underground widened part includes the following steps for: removing a segment of a shield tunnel and constructing a starting base for a shield machine used for forming an underground widened part around the shield tunnel; starting a preceding shield machine from the starting base and installing a plurality of preceding shields in a ring form leaving an interval, the preceding shield having a segment for cutting disposed thereon; starting a following shield machine from the starting base and installing a plurality of following shields in a ring form while cutting a part of the preceding shield; forming a water cutoff area on outer periphery of the preceding shield and the following shield; connecting the preceding shield with the adjacent following shield and configuring a ring-form outer shell shield outside of the shield tunnel, thus forming an outer shell for the underground widened part; and excavating inside the outer shell shield after configuring the outer shell shield.SELECTED DRAWING: Figure 2 |
申请公布号 |
JP2016153601(A) |
申请公布日期 |
2016.08.25 |
申请号 |
JP20160109914 |
申请日期 |
2016.06.01 |
申请人 |
MAEDA CORP |
发明人 |
MORI YOSHIKI;YASUMITSU TATSUYA;SHINOHARA KEIJI;TANABE KAZUYA;MORITA ATSUSHI;TAKEBE TOKUJI |
分类号 |
E21D9/04;E21D9/06;E21D11/00 |
主分类号 |
E21D9/04 |
代理机构 |
|
代理人 |
|
主权项 |
|
地址 |
|