PROBLEM TO BE SOLVED: To provide a construction method for a reinforced concrete structure for enabling a shorter construction period.SOLUTION: Reinforcement work for beams 52 on a N+1th floor and form work for a floor on the N+1th floor are performed in prior to another work, and reinforcement work for the beams 52 on the N+1th floor and the installation of forms, reinforcement work for walls on a Nth floor and the installation of forms of the walls and columns, reinforcement work for the floor on the N+1th floor, and reinforcement work for columns 51 are performed collaterally at the same time. |