发明名称 Contingency screening in multi-control area electrical power systems using coordinated DC power flow
摘要 A new approach in contingency analysis is presented based on a modular method for power flow calculation. The proposed method exploits reuse of power flow data for modules not affected by an outage. The method minimizes the number of necessary computations and matrix inversions in contingency analysis; this is achieved by recalculating only the modules affected by the change and reusing data from the original system for all other modules.
申请公布号 US9625887(B2) 申请公布日期 2017.04.18
申请号 US201313958248 申请日期 2013.08.02
申请人 Carnegie Mellon University 发明人 Ilic Marija;Cvijic Sanja
分类号 G05D3/12;G05B15/02;H02J3/06;H02J3/00 主分类号 G05D3/12
代理机构 Downs Rachlin Martin PLLC 代理人 Downs Rachlin Martin PLLC
主权项 1. A method of performing a contingency screening of an electrical power network, the method comprising: receiving a previously computed, modular representation of the electrical power network, wherein the modular representation includes: a zoomed-in representation defined by a first plurality of variables and having internal line connections; anda zoomed-out representation defined by a second plurality of variables and having tie-line connections,wherein the first plurality of variables includes at least one variable not included in the second plurality of variables and at least one of the second plurality of variables is derived from a linear combination of line flows of two or more of the internal line connections; receiving a line outage having an outage type, including receiving a line outage for which the outage type is an internal outage; determining whether to recompute the zoomed-out representation or both of the zoomed-in and zoomed-out representations as a function of the outage type, including determining that both of the zoomed-in and zoomed-out representations need to be recomputed based on the internal outage; and recomputing, based on the line outage, the one(s) of the zoomed-in and zoomed-out representations determined at said determining step, including recomputing both of the zoomed-in and zoomed-out representations as a function of the internal outage; wherein recomputing the zoomed-out representation includes recomputing the zoomed-in representation to account for an outage and performing a forward transformation as a function of the recomputed zoomed-in representation to produce a recomputed zoomed-out representation.
地址 Pittsburgh PA US