摘要 |
A start-up method of a steam turbine plant includes a first step and a second step. The first step is performed at an aeration start time. In the first step, a reheat steam pressure of an aeration boiler is set to be a reheat steam pressure required by a steam turbine or less. Besides, a reheat steam pressure of a standby boiler is set to be a reheat steam pressure required for the standby boiler or more. The second step is performed when a load of the steam turbine becomes a predetermined value. In the second step, the reheat steam pressure of the aeration boiler is increased to the same degree as the reheat steam pressure of the standby boiler. After that, steam from the aeration boiler and steam from the standby boiler are merged to be supplied to the steam turbine. |