发明名称 蒸気タービンプラントの起動方法
摘要 A start-up method of a steam turbine plant includes a first step and a second step. The first step is performed at an aeration start time. In the first step, a reheat steam pressure of an aeration boiler is set to be a reheat steam pressure required by a steam turbine or less. Besides, a reheat steam pressure of a standby boiler is set to be a reheat steam pressure required for the standby boiler or more. The second step is performed when a load of the steam turbine becomes a predetermined value. In the second step, the reheat steam pressure of the aeration boiler is increased to the same degree as the reheat steam pressure of the standby boiler. After that, steam from the aeration boiler and steam from the standby boiler are merged to be supplied to the steam turbine.
申请公布号 JP6067535(B2) 申请公布日期 2017.01.25
申请号 JP20130221204 申请日期 2013.10.24
申请人 株式会社東芝 发明人 一瀬 麻衣;田尾 浩之;木下 敦夫
分类号 F01D19/00;F22B35/00 主分类号 F01D19/00