发明名称 Method of providing a support column
摘要 A primary earth penetrating mandrel formed of a hollow shell steel plate has an upper end and an open lower end joined by an upwardly and outwardly tapered wall. The mandrel is driven downwardly in the earth to simultaneously form a vertical cavity while compacting the sidewall of the cavity to provide structural integrity. The mandrel is then moved upwardly from the bottom of the cavity and aggregate is deposited in the bottom of the cavity following which the mandrel is lowered so that its lower end engages the deposited aggregate and densifies the aggregate by vertical vibratory action and static force with these steps being repeated until the pier top is near the surface of the earth. A second embodiment includes a conduit in the primary mandrel for injecting concrete or grout into aggregate previously deposited in the cavity.
申请公布号 US9243379(B2) 申请公布日期 2016.01.26
申请号 US201314070756 申请日期 2013.11.04
申请人 Geopier Foundation Company, Inc. 发明人 Wissmann Kord J.;Moxhay Alan L.;Fox Nathaniel S.
分类号 E02D3/08;E02D5/46;E02D5/38;E02D7/00;E02D7/02 主分类号 E02D3/08
代理机构 Nexsen Pruet, PLLC 代理人 Nexsen Pruet, PLLC
主权项 1. A method of forming an aggregate pier comprising the steps of: (a) driving downwardly into pier site soil a mandrel having an open lower end initially covered by a cap to form a cavity to a desired depth for said aggregate pier while supporting a sidewall of the cavity, wherein the mandrel is tapered along a substantial portion of its length; (b) moving the mandrel upwardly towards a top of said cavity so as to separate said cap from said open end of the mandrel while delivering loose aggregate through said open end of the mandrel and depositing said delivered aggregate to the cavity so as to support said sidewall below said upwardly moved mandrel; (c) using the mandrel and one or more new caps to repeat said steps (a) and (b) at one or more different portions of the pier site so as to form a plurality of said aggregate deposited cavities; (d) driving downwardly into one of the plurality of said aggregate deposited cavities the mandrel so that said lower end of the mandrel compacts said deposited aggregate and densifies said soil; (e) moving said mandrel upwardly from said compacted aggregate and depositing additional loose aggregate in said one of the plurality of cavities; and (f) repeating said steps (d) and (e) at each of said plurality of aggregate deposited cavities until a plurality of pier components of a desired height is formed.
地址 Davidson NC US