摘要 |
<p><P>PROBLEM TO BE SOLVED: To reduce processes and costs by reducing the temporary reinforcement for overturn prevention and temporary reinforcement during movement of a storage external wall on the premise of moving(building-moving) the storage external wall in order to use the external wall of an existing building as a part of the external wall of a new building. <P>SOLUTION: The skeleton construction of a new building is performed at a plane position prior to the movement of a storage external wall 1, and before the storage external wall 1 is moved, the storage external wall 1 is integrated with a structure frame 2 of the new building, and the storage external wall 1 and the structure frame 2 of the new building are simultaneously moved to the position of the new building by a building-movement method, and the structure frame 2 of the new building is integrated with a foundation. <P>COPYRIGHT: (C)2013,JPO&INPIT</p> |