发明名称 |
METHOD FOR PREVENTING WATER USED IN LAND RECLAMATION |
摘要 |
PURPOSE: A construction method of a cofferdam for land reclamation is provided to construct a cofferdam easily and to reduce the cost and time required for cofferdam construction even if the water level difference between the inside and the outside and the speed of a current due to a decrease in the cross sectional area of flow. CONSTITUTION: A construction method of a cofferdam for land reclamation comprises the steps of installing many piles in a portion of a cofferdam construction area(S10), constructing a bank to an pile installation area(S20), and installing a cofferdam installation material to the pile installation area, thereby completing the final cofferdam(S30). |
申请公布号 |
KR20110060684(A) |
申请公布日期 |
2011.06.08 |
申请号 |
KR20090117344 |
申请日期 |
2009.11.30 |
申请人 |
SUNG LIM KODERA CO., LTD. |
发明人 |
AN, SANG MIN |
分类号 |
E02B3/18;E02B3/10;E02B3/12 |
主分类号 |
E02B3/18 |
代理机构 |
|
代理人 |
|
主权项 |
|
地址 |
|