发明名称 METHOD FOR PREVENTING WATER USED IN LAND RECLAMATION
摘要 PURPOSE: A construction method of a cofferdam for land reclamation is provided to construct a cofferdam easily and to reduce the cost and time required for cofferdam construction even if the water level difference between the inside and the outside and the speed of a current due to a decrease in the cross sectional area of flow. CONSTITUTION: A construction method of a cofferdam for land reclamation comprises the steps of installing many piles in a portion of a cofferdam construction area(S10), constructing a bank to an pile installation area(S20), and installing a cofferdam installation material to the pile installation area, thereby completing the final cofferdam(S30).
申请公布号 KR20110060684(A) 申请公布日期 2011.06.08
申请号 KR20090117344 申请日期 2009.11.30
申请人 SUNG LIM KODERA CO., LTD. 发明人 AN, SANG MIN
分类号 E02B3/18;E02B3/10;E02B3/12 主分类号 E02B3/18
代理机构 代理人
主权项
地址