发明名称 Recovery Maturity Model (RMM) for readiness-based control of disaster recovery testing
摘要 A Recovery Maturity Model (RMM) is used to determine whether a particular Information Technology (IT) production environment can be expected, with some level of confidence, to successfully execute a test for disaster recovery (DR). The RMM provides a quantitative analysis in terms of the extent to which best practices are seen to have been implemented as a set of categories for elements of the environment and multiple elements for each category. A summation of the scoring elements, which may be a weighted summation, results in an overall quantitative metric which is then used to control whether or not testing will proceed.
申请公布号 US9208006(B2) 申请公布日期 2015.12.08
申请号 US201313792713 申请日期 2013.03.11
申请人 SUNGARD AVAILABILITY SERVICES, LP 发明人 Jones Steven;Maldonado Jose
分类号 G06F11/00 主分类号 G06F11/00
代理机构 Cesari and McKenna, LLP 代理人 Cesari and McKenna, LLP
主权项 1. A method for determining disaster recovery readiness for a data processing environment which includes one or more physical and/or virtual data processing infrastructure elements, and where a disaster recovery (DR) service is capable of providing disaster recovery for the infrastructure elements, the method comprising: a. storing information in a Recovery Maturity Model (RMM) representing one or more criteria indicative of expected successful DR test execution based on best practices, the RMM further comprising a model associating infrastructure element types with recovery maturity elements, wherein the infrastructure element types include an application type, recovery backup technology, a network type, physical machines operating system(s), virtual machines operating system(s), and physical processor type, and the recovery maturity elements comprise at least a recovery configuration completed, recovery backup assessment, recovery strategy defined, recovery procedure developed, DR kit completeness, Recovery Time Objective achievable, Recovery Point Objective achievable, and knowledge transfer completed; b. accepting data, via a user interface, representing one or more evaluations of one or more of the criteria specified in the RMM, where the user interface accepts the evaluations as a numerical score for each infrastructure element type and each further recovery maturity element, to thereby determine a matrix of numerical scores; c. determining if the environment is ready for DR testing by comparing one or more of the evaluation(s) to predetermined information; and d. if the environment is determined to be ready for DR testing, enabling at least one DR test for execution.
地址 Wayne PA US