摘要 |
During renovation of a ballast bed of a track, old bulk material (6) to be removed is stored on a number of storage wagons (2), forming a track construction site (10), said storage wagons being connected to form a loading train (7). In parallel to this, new bulk material (9) is introduced into the track construction site (10), said new bulk material being pre-stored on a number of storage wagons (2), which are connected to form a loading train (8). The introduction of the new bulk material (9) into the track construction site (10) is controlled automatically depending on a volume of the old bulk material (6) removed from the track construction site (10). |