摘要 |
A procedure for controlling a renewable energy generation plant (1 ), where said plant (1 ) features multiple primary energy converters (2) connected with controllable energy converters (3) and a controller (10) to control the energy converters (3), consists of the following steps: - Assign at least one energy converter (3) to a primary group (7) of energy converters (3) set to maximum power output by the controller (10). - Assign energy converters (3) to at least one other group (8, 9) of energy converters (3) set to reduced power output by the controller (10), so that the desired total output of the renewable energy generation plant (1 ) is set by assigning the energy converters (3) to the groups (7, 8, 9). - Collect power data on the first group (7) of energy converters (3). - Determine the total potential output power available from the renewable energy generation plant (1 ) based on the power data collected from the first group (7) of energy converters (3). |