The present invention relates to a method for driving a pile using a jig. According to the present invention, the method for driving a pile using a jig comprises: a step of determining the location of a plurality of piling points and the inclination value of piles in each point; a step of storing information on the location of each point; a step of designing a moving path by connecting the points to each other; a step of arranging a pile driving ship at the first point of the moving path using the information on the location of each point; and a step of moving the pile driving ship along the moving path to construct the piles by adjusting the angle of a pile driving jig prepared in the ship in accordance with the inclination value of the piles in each point.