发明名称 INSTALLATION DEVICE AND INSTALLATION METHOD FOR LINING CONCRETE WALL WITHIN TUNNEL
摘要 PROBLEM TO BE SOLVED: To improve work efficiency by reducing stage replacement work when moving forms in accordance with a method of construction for improving the quality of lining concrete wall within the tunnel by prolonging a curing term of the lining concrete wall within the tunnel by alternately using a plurality of forms.SOLUTION: A plurality of installation areas to install therein forms 2, 3 which may take diameter enlarged states W2, W3 and a diameter reduced state S2 are arranged side by side with each other in a length direction X within a tunnel 1. The plurality of installation areas include a front area P1 at a side of an installation progressing direction XF, a rear area Q1 at a side of an opposite direction XB to the installation progressing direction XF, and an intermediate area R1 between the front area P1 and the rear area Q1. When performing installation successively from the form 2 installed in the rear area Q1, the preceding form 2 brought into the diameter reduced state S2 can be moved to the front area P1 through the inside of the following forms 3 in the diameter enlarged states W2, W3. A movable stage 6 of a support stand 4 has such a length as to support the forms 2, 3, thereby moving from a retracting position 4B over the rear area Q1 and the intermediate area R1 to a forward position 4F over the intermediate area R1 and the front area P1. A transfer stage 7 of the support stand 4 for supporting the form 2 in the diameter reduced state S2 is capable of reciprocating in the length direction X on the movable stage 6. Thus, work efficiency is improved by reducing stage replacement work when moving the forms 2, 3.
申请公布号 JP2014070459(A) 申请公布日期 2014.04.21
申请号 JP20120219444 申请日期 2012.10.01
申请人 OHBAYASHI CORP;GIFU KOGYO CO LTD 发明人 KUGE ATSUSHI;NISHIURA HIDEAKI;AKIYOSHI KENJI;IWAMOTO SHUNICHI;NIWAYA JUNICHI;OKUBO TSUNEHIDE
分类号 E21D11/10 主分类号 E21D11/10
代理机构 代理人
主权项
地址