摘要 |
Methods and apparatuses are described for creating and using full-kit tasks, monitoring the progress of full-kit tasks, determining full-kit dates, checking compliance of release conditions associated with full-kit tasks, and/or computing and reporting full-kit task delays. A full-kit task can be used in the project plan to represent the preparations that are required or recommended to be performed before executing a set of tasks. The full-kit task can be a zero-duration task that has a full-kit date and that includes a list of items which need to be completed by the full-kit date. The full-kit task is capable of being in one of the following states: not started, in progress, released, and completed. In some embodiments, the set of tasks associated with the full-kit task can only be started if the full-kit task is either in the released state or the completed state. |