发明名称 STARTING METHOD FOR PRESSURIZED FLUIDIZED BED COMBINED CYCLE POWER GENERATION PLANT
摘要 PROBLEM TO BE SOLVED: To provide a starting method for a pressurized fluidized bed combined cycle power generation plant that can start the pressurized fluidized bed combined cycle power generation plant even when the air supply capacity of an in-house air system decreases.SOLUTION: In a starting method for a pressurized fluidized bed combined cycle power generation plant that performs backflow preventing operation to supply backflow preventing air to a pressurized fluidized bed boiler so as to prevent a combustor combustion gas from flowing back to the pressurized fluidized bed boiler when a gas turbine is actuated, mixed air of air of an in-house air system 101 and air of an air system 111 for control is used as the backflow preventing air. The mixed air is produced by using a backup system 130 connecting the in-house air system 101 and air system 111 for control to each other, in the reverse direction, and sending air from the air system 111 for control to the in-house air system 101.
申请公布号 JP2013221700(A) 申请公布日期 2013.10.28
申请号 JP20120094308 申请日期 2012.04.18
申请人 CHUGOKU ELECTRIC POWER CO INC:THE 发明人 YAMAMOTO MASAMI;SAKO KOJI
分类号 F23C10/16;F02C7/26;F02C9/28;F02C9/50;F23C10/28 主分类号 F23C10/16
代理机构 代理人
主权项
地址