PURPOSE: A ship construction method is provided to improve productivity with reduced construction time because the blocks are welded right after loading by correcting the position of the blocks in advance. CONSTITUTION: A ship construction method is as follows. The size of a main block and a PE block is measured(S110). The measured data of the main block and the PE block are matched(S120). If the measured data are not matched, the PE block is corrected to be matched with the main block(S130). The PE block is installed in the main block(S140). [Reference numerals] (S110) Measure the sizes of a main block and a PE block; (S120) Match the measured data of the main block and the PE block; (S130) Correct the main block and the PE block to be matched with each other; (S140) Install the PE block in the main block; (S141) Load the corrected PE block on the main block; (S143) Weld the main block and the PE block
|