发明名称 HYDRAULIC POWER PLANT MONITORING CONTROLLER
摘要 <P>PROBLEM TO BE SOLVED: To provide a hydraulic power plant monitoring controller that allows a power system to be stably operated by obtaining a highly accurate flow-down delay time period. <P>SOLUTION: One embodiment of the present invention relates to a hydraulic power plant monitoring controller for performing monitoring control of facilities installed at an upstream dam, a generator and a downstream dam that constitute a hydraulic power plant. Further, the hydraulic power plant monitoring controller comprises: upstream dam discharge start time storage means for calculating upstream dam discharge start time indicating time when the discharge is started from the upstream dam; power generation start time storage means for calculating power generation start time indicating time when the generator starts to generate power; downstream dam water introduction start time storage means for calculating downstream dam water introduction start time indicating time when water introduction to the downstream dam is started; and flow-down delay time period calculation means for calculating a flow-down delay time period indicating a time period from the time when the discharge is started from the upstream dam to the time when the water introduction to the downstream dam is started from the upstream dam discharge start time, the power generation start time and the downstream dam water introduction start time. <P>COPYRIGHT: (C)2013,JPO&INPIT
申请公布号 JP2013078179(A) 申请公布日期 2013.04.25
申请号 JP20110215713 申请日期 2011.09.29
申请人 TOSHIBA CORP 发明人 SAWAZAKI KAZUO;ONISHI MASAMI;TAKEUCHI MICHIE;SHINGU KAZUMI;MIYATA MASATOSHI;NOMURA NAO
分类号 H02J3/00 主分类号 H02J3/00
代理机构 代理人
主权项
地址