<P>PROBLEM TO BE SOLVED: To provide an embankment construction method for short-term restoration of an embankment destroyed by a flood and replacement with a permanent embankment. <P>SOLUTION: The first invention relates to a construction method for a temporary embankment, in which a core section of the embankment is constituted by disposing unit members vertically and horizontally, in which intrusion of sediment into the core section is prevented by wrapping a peripheral side section of the core section and an upper section thereof in a protective sheet, in which an upward raised and opened entrance/exit hole is provided in the upper section of the core section, and in which soil is heaped up around the core section and constructed as the temporary embankment. The second invention relates to an embankment construction method for constructing a permanent embankment by pouring a solidification material into the core section of the temporary embankment. <P>COPYRIGHT: (C)2013,JPO&INPIT |