Method of construction of underground power lines in trunk road, involves laying high voltage underground cable in specific lane of trunk road and moving cable of respective lanes as close as possible
摘要
#CMT# #/CMT# The method involves laying high voltage underground cable in specific lane of trunk road. The cable of respective lanes is moved as close as possible at a distance of 0.11-2 m. The underground cable is laid in channels together with power transmission system and waste disposal system and the diameter of the channels is set to 1-2 m. #CMT#USE : #/CMT# Method of construction of underground power lines in trunk road. #CMT#ADVANTAGE : #/CMT# The environmental protection is improved. The electromagnetic pollution and generation of noise are reduced. The landscape and bird conservation are improved. The raw material used for the construction of the power line is reduced. The transmission losses are minimized. The maintenance costs of the power lines are reduced.