发明名称 System for supporting carry-in operation planning
摘要 A carry-in ready period calculation part calculates a candidate of a carry-in ready period which is a period during which a carry-in operation can be conducted and outputs the candidate in an output part so as to make entire construction works efficient. The calculation is performed based on a site arrival time schedule which is a time schedule showing when a carry-in target equipment arrives at a site, a temporary placement time schedule which is a time schedule showing when the equipment arrived is temporarily placed, and a construction time schedule of a building in which the equipment is carried.
申请公布号 US8326664(B2) 申请公布日期 2012.12.04
申请号 US201113151540 申请日期 2011.06.02
申请人 FUKUDA YOSHIBUMI;YOKOTA TAKESHI;YAMANE KENICHIROU;AKAGI KENJI;MORITA KENSUKE;HITACHI-GE NUCLEAR ENERGY, LTD. 发明人 FUKUDA YOSHIBUMI;YOKOTA TAKESHI;YAMANE KENICHIROU;AKAGI KENJI;MORITA KENSUKE
分类号 G06Q10/00;E04G21/00;G06Q50/00;G06Q50/08 主分类号 G06Q10/00