发明名称 METHOD FOR CRITICAL PATH SCHEDULING OF ACTIVITY TIME SEGMENTS
摘要 A project management scheduling method applies critical path scheduling to separate the duration of each activity of the project into a group of segmented time segments attached to each other. The computer implemented method converts all activity relationships into finish-to-start between time segments without lead or lag times and corrects float and critical path calculations. Additional time segments representing daily events having either a positive or negative effect on time segment duration can be inputted and the project schedule adjusted accordingly. The method can also be employed in the conversion of existing critical path method scheduling systems.
申请公布号 US2012265570(A1) 申请公布日期 2012.10.18
申请号 US201213426553 申请日期 2012.03.21
申请人 HEGAZI TAREK MOHAMED MOHAMED 发明人 HEGAZI TAREK MOHAMED MOHAMED
分类号 G06Q10/06 主分类号 G06Q10/06
代理机构 代理人
主权项
地址