发明名称 |
Method of installing a cable in the tower of a wind power plant |
摘要 |
A method and apparatus for mounting at least one line in a tower of a wind power plant, the line is provided in the tower before its erection in shortened, preferably folded or wound-up form. The tower also includes a means for extending the line, after erection of the tower so that the lower end of the line is lowered in a controlled manner to the bottom of the tower and can be attached there to a connector and the upper end is extended to a connector at the top of the tower if not already connected to the connector.
|
申请公布号 |
US8230660(B2) |
申请公布日期 |
2012.07.31 |
申请号 |
US20100807768 |
申请日期 |
2010.09.14 |
申请人 |
MUEHLHAEUSER MARKUS;SCHULER PRESSEN GMBH & CO, KG |
发明人 |
MUEHLHAEUSER MARKUS |
分类号 |
E04B1/00;E04C3/00;E04H12/00 |
主分类号 |
E04B1/00 |
代理机构 |
|
代理人 |
|
主权项 |
|
地址 |
|