摘要 |
Method for setting up a condensation plant, for which two tube bundles (2, 3) are placed on a roof-shaped preassembly frame (1) and connected to one another in a first area. The tube bundles (2, 3,), along with the base plates (5, 6) thereof which hold the heat-exchanger tubes, are placed in supports (10) at a roof ridge strut (11) of the preassembly frame (1) in such a way that the mutually facing longitudinal sides (12, 13) of the base plates (5, 6) can be welded together by means of a root seam, before the preassembled roof-shaped tube bundle delta (14) is lifted from the preassembly frame (1) and brought into the installed position. |