发明名称 CONTROL SYSTEM AND HYDROELECTRIC POWER PLANT
摘要 <P>PROBLEM TO BE SOLVED: To provide a control system and a hydroelectric power plant, capable of sufficiently obtaining a backwash effect even when the turbidity of intake water is high. <P>SOLUTION: The control system installed in a run-off-river hydroelectric power plant for controlling the backwash of a backwashable strainer having a water intake position on the upstream of a generator inside a water channel includes: a detector which is installed on the upstream of the water intake position of strainer and detects the turbidity of the water; and a control part which sets the frequency of the backwash of the strainer corresponding to the turbidity of the water detected by the detector. <P>COPYRIGHT: (C)2012,JPO&INPIT
申请公布号 JP2012057325(A) 申请公布日期 2012.03.22
申请号 JP20100199789 申请日期 2010.09.07
申请人 CHUGOKU ELECTRIC POWER CO INC:THE 发明人 TAKETO KATSUHIKO
分类号 E02B9/00;B01D24/00;B01D29/00;B01D29/11;B01D29/66;B01D29/96;B01D35/02 主分类号 E02B9/00
代理机构 代理人
主权项
地址