发明名称 JOINT METHOD FOR H-BEAM AND CONSTRUCTION METHOD FOR BASEMENT STRUCTURE WITHOUT TEMPORARY STRUCTURE USING THE SAME
摘要 PURPOSE: A connection method for an H-beam and a construction method for an underground structure without a temporary structure using the same are provided to remarkably reduce construction costs because the installation and dismantling works of a temporary structure are not required. CONSTITUTION: A connection method for an H-beam is as follows. An upper reinforcing plate(410) is coupled to the top surface of upper flanges of H-beams(400). A lower reinforcing plate is coupled to the bottom surface of lower flanges of the H-beams. A temporary space control member(20), which maintains a space between the H-beams, is removed.
申请公布号 KR20110136062(A) 申请公布日期 2011.12.21
申请号 KR20100055834 申请日期 2010.06.14
申请人 YANG, SUK GEONG 发明人 YANG, SUK GEONG
分类号 E02D29/045 主分类号 E02D29/045
代理机构 代理人
主权项
地址