摘要 |
Method of filling working out space of a deep open-pit includes delivery of rock dump material with utility vehicles, its unloading to receiving pit formed of that very rock lower than the level of transportation lanes. First receiving pit is equipped in virgin rock mass of the first from above ledge of the worked out open-pit, displacement of the rock from it is carried out in direction towards the upper edge of the dump first with bulldozer, and then - with wheel loader with filled surface in passes along the side of the worked out open-pit, at that in the process of filling one reveals stable zones of compacting of the backfilled rocks at angle of natural slope, those are located with boundary on the surface of the dump and each time at displacement of those one moves the receiving pit and transportation lanes closer to that, and so till complete filling of the open-pit. |