摘要 <p><P>PROBLEM TO BE SOLVED: To provide a construction method of a tunnel easily adjusting an error between a main tunnel and a branch tunnel in a width extended part and a joint part of the tunnel. <P>SOLUTION: In this construction method, a clearance is formed between opposing end faces of a lining segment 6 and a connection segment 9 to make an interval between end parts on an upper side larger than an interval between end parts on a lower side, an adjusting board 73 having end parts being parallel with the end parts of the lining segment 6 and the connection segment 9 is dropped in between both of the segments 6 and 9, and then concrete 20 is placed between both of the segments. <P>COPYRIGHT: (C)2011,JPO&INPIT</p>
申请公布号 JP2011080284(A) 申请公布日期 2011.04.21
申请号 JP20090234013 申请日期 2009.10.08
申请人 NISHIMATSU CONSTR CO LTD 发明人 MITO KENJI;OE IKUO;AKUTAGAWA MITSUSHI
分类号 E21D9/01;E21D9/06;E21D13/02 主分类号 E21D9/01