发明名称 |
CONSTRUCTION METHOD BY CONCRETE LINING IN PARALLEL WITH EXCAVATION, WORKING PLATFORM FOR REINFORCEMENT AND WATERPROOFING WORK AND LINING FORM FOR POURING LINING CONCRETE |
摘要 |
PURPOSE: A tunnel construction method through simultaneous excavation and lining construction, a working truck, and a lining form used for a tunnel construction method are provided to reduce construction times through simultaneous excavation and lining construction and improve construction safety. CONSTITUTION: A tunnel construction method through simultaneous excavation and lining construction comprises following steps. Forward excavation is carried out. The excavation is continuously carries out and a working truck is placed in a section in which the excavation is completed, so waterproof construction is carried out and a lining bar is placed. The working truck is moved forward, and the waterproof construction and the arrangement work of lining bars are continuously carried out. A lining form is arranged in the section where the lining bar is arranged, so the lining concrete is poured and cured. The lining form is moved forward.
|
申请公布号 |
KR101014779(B1) |
申请公布日期 |
2011.02.14 |
申请号 |
KR20090097703 |
申请日期 |
2009.10.14 |
申请人 |
E-HWA INDUSTRY CO., LTD.;SAMSUNG C&T CORPORATION |
发明人 |
KIM, JANG DEUK;RYOO, YEUNG SUN;MOON, BYOUNG TAG;KIM, JEONG WON;KIM, SANG IL |
分类号 |
E21D9/00;E21D11/40 |
主分类号 |
E21D9/00 |
代理机构 |
|
代理人 |
|
主权项 |
|
地址 |
|