发明名称 |
SHOE CONSTRUCTION METHOD FOR PREFABRICATED PRESTRESSED GIRDER AND PREFABRICATED PRESTRESSED GIRDER BRIDGE CONSTRUCTION METHOD |
摘要 |
PURPOSE: A construction method of a hollow girder, and a bridge bearing of the hollow girder is provided to improve structural safety and construction performance by reducing the amount of installed bridge bearings. CONSTITUTION: A construction method a bridge bearing of a hollow girder is as follows. Bridge bearings(300) are installed in the bottom space between hollow girders(100). One bridge bearing is installed between two hollow girders. Concrete(400) is placed in the gap between the hollow girders. Studs(340) are protruded from the top of the bridge bearings, and buried in the concrete. |
申请公布号 |
KR20100034098(A) |
申请公布日期 |
2010.04.01 |
申请号 |
KR20080093047 |
申请日期 |
2008.09.23 |
申请人 |
SAMPYO ENGINEERING & CONSTRUCTION LTD. |
发明人 |
KIM, HYEON SU;KIM, SUNG JAE |
分类号 |
E01D2/04;E01D2/00;E01D19/04 |
主分类号 |
E01D2/04 |