摘要 |
<p><P>PROBLEM TO BE SOLVED: To provide a construction planning support system for a plant, wherein estimation accuracy of man-hours of installation work of the actual plant is greatly improved. <P>SOLUTION: The construction planning support system for the plant has a 3D-CAD database related to components of a work object, a process database related to installation of the components, and a man-hour expression database related to the work man-hours required for the installation of the components, and has a man-hour calculation part calculating the man-hours for installing the components constituting the plant. The man-hour calculation part has: a work object attribute calculation part calculating a work object attribute of the work; a workspace situation calculation part calculating a workspace situation of the work changing according to progress of construction work and the work object attribute of the work; and a work man-hour calculation part calculating work man-hours in an execution period of the work. <P>COPYRIGHT: (C)2010,JPO&INPIT</p> |