发明名称 PILE CONSTRUCTING METHOD FOR REINFORCING ENDS AND THE PILE CONSTRUCTED BY THIS
摘要 PURPOSE: A pile construction method for reinforcing a front end and a pile built by the same are provided to reduce the number of piles and reduce construction period by increasing support force. CONSTITUTION: A pile construction method for a reinforcing a front end comprises following steps. A pile body is pressed and inserted inside the ground. An excavating unit(1) is inserted inside the pile body and a foundation is formed. The excavating unit is drawn out from the pile body and spays fluid inside the foundation, so the slime within the foundation is discharged. The foundation is filled with the filler.
申请公布号 KR20100026486(A) 申请公布日期 2010.03.10
申请号 KR20080085509 申请日期 2008.08.29
申请人 YOON, IN BYUNG;PDTENC CO., LTD.;CHOO JIN CONSTRUCTION CO., LTD. 发明人 YOON, IN BYUNG;KIM, NAM SUN
分类号 E02D5/30;E02D5/28;E02D5/46 主分类号 E02D5/30
代理机构 代理人
主权项
地址
您可能感兴趣的专利