发明名称 |
Installing piles or tunnel setions using two or more syncronised impact drivers |
摘要 |
An arrangement (1) for installing building elements having a diameter in excess of 5 meters, and for installing tunnel sections, into a ground formation is disclosed. The arrangement includes a building element (2), on which two or more impact drivers (3) for delivering blows to the element (2) are mounted. The arrangement further has a control system for synchronising the blows to be delivered to the element (2), wherein the control system is able to synchronise the blows within 10 milliseconds.
|
申请公布号 |
NZ552864(A) |
申请公布日期 |
2009.09.25 |
申请号 |
NZ20050552864 |
申请日期 |
2005.07.26 |
申请人 |
IHC HOLLAND IE B.V. |
发明人 |
HESSELS, JOHANNES LOUIS LEONARDUS;VAN FOEKEN, ROBERT JAN;VAN DUIJVENBODEN, ARRIS |
分类号 |
E02D7/00;E02D7/06;F15B21/02 |
主分类号 |
E02D7/00 |
代理机构 |
|
代理人 |
|
主权项 |
|
地址 |
|