发明名称 CONFIGURATION METHOD OF WATERPROOF LAYER AND ITS CONSTRUCTION METHOD
摘要 PROBLEM TO BE SOLVED: To prevent water from invading through a lower end of a waterproof layer when a difference in level is caused at a foundation top end or a building or external heat insulation is carried out. SOLUTION: A waterproof member arranged at the lower end of the waterproof layer is installed before a wall constituent member or the like which requires waterproof is installed and raised after the wall constituent member or the like requiring waterproof is installed. By this, the waterproof layer is configured at the periphery of the lower end including its cut end of the wall constituent member or the like requiring waterproof, and the invasion of water to the wall constituent member or the like requiring waterproof is prevented. COPYRIGHT: (C)2009,JPO&INPIT
申请公布号 JP2009215864(A) 申请公布日期 2009.09.24
申请号 JP20080100827 申请日期 2008.03.12
申请人 AMERICAN SILVERWOOD INC 发明人 MIYACHI SOICHIRO;UEDA KIYOHIKO
分类号 E04F13/08 主分类号 E04F13/08
代理机构 代理人
主权项
地址