摘要 |
PROBLEM TO BE SOLVED: To provide molten metal pouring equipment where a required molten metal pouring time is secured, and a molten metal pouring speed can be made high. SOLUTION: The molten metal pouring equipment is arranged between an upstream side carrier line carrying a molded die and a downstream side carrier line carrying the die into which molten metal is poured, and comprises: two molten metal pouring machines 2a, 2b arranged in such a manner that the molten metal pouring positions are made parallel to the horizontal directions of the two carrier lines; two traversers 3a, 3b installed between the two carrier lines in the front positions of the two molten metal pouring machines and to the directions orthogonal to the two carrier lines; running carts respectively placed on the traversers and runnable on the traversers; and roller units 6a, 6b, 7a, 7b installed in the respective running carts and capable of carrying the die from the upstream side carrier line to the downstream side carrier line. COPYRIGHT: (C)2009,JPO&INPIT
|