发明名称 CONSTRUCTING METHOD OF TOP-DOWN TYPE RETAINING WALL
摘要 A constructing method of top-down type retaining wall for vertical cut slope, using a partially buried H-pile, is provided to construct a retaining wall for vertical cut slope at low cost without installation of temporary structure. A constructing method of top-down type retaining wall for vertical cut slope comprises a step of setting up an H-pile(20) in the ground so that only a part of the H-pile is buried in a filler, a step of excavating the ground in front of the H-pile so that the rest part of the H-pile is exposed, a step of setting up a concrete wall(40) by applying concrete between the exposed portion of the H-pile and the front side of the ground, and a step of forming a retaining wall by stacking retaining wall blocks(70) successively, wherein the retaining wall block is composed of a pile block(71) positioned in front of the H-pile and a middle block(72) positioned between the pile blocks.
申请公布号 KR20090055793(A) 申请公布日期 2009.06.03
申请号 KR20070122616 申请日期 2007.11.29
申请人 SMARTEC ENGINEERING CO., LTD.;I SAN CO., LTD. 发明人 HONG, SUNG YOUNG
分类号 E02D29/02 主分类号 E02D29/02
代理机构 代理人
主权项
地址