发明名称 SHIELD TUNNEL CONSTRUCTION METHOD
摘要 PROBLEM TO BE SOLVED: To provide a shield tunnel construction method in which segments are held on the ground by a natural ground holding material having fluidity, and a pressurized state is maintained even after filling of a back-filling material. SOLUTION: The shield tunnel construction method is carried out by assembling the segments on a rear trunk portion of a shield machine having excavated the natural ground, and thereafter, filling the back-filling material in a gap between the assembled segments and the natural ground. According to the method, the natural ground holding material having fluidity is filled in the gap between the assembled segments and the natural ground, and thereafter, recovering the filled natural ground holding material, followed by filling the back-filling material, to thereby harden the back-filling material between the assembled segments and the natural ground. COPYRIGHT: (C)2009,JPO&INPIT
申请公布号 JP2008291507(A) 申请公布日期 2008.12.04
申请号 JP20070137937 申请日期 2007.05.24
申请人 SHIMIZU CORP 发明人 SUGIYAMA HIROKAZU;GOTO SHIGERU
分类号 E21D11/00 主分类号 E21D11/00
代理机构 代理人
主权项
地址