发明名称 Method for providing auxiliary power to an electric power plant using fischer-tropsch technology
摘要 A method for meeting both base-load and peak-load demand in a power production facility. By integrating a Fischer-Tropsch (FT) hydrocarbon production facility with an electrical power generating facility, peak-load power demand can be met by reducing the temperature of the FT reactor thereby increasing the quantity of tail gases and using FT tail gases to fuel a gas turbine generator set. The method enables rapid power response and allows the synthesis gas generating units and the FT units to operate with constant flow rates.
申请公布号 US2008223046(A1) 申请公布日期 2008.09.18
申请号 US20050316455 申请日期 2005.12.21
申请人 YAKOBSON DENNIS L;CORKADEL CLAUDE C;BENHAM CHARLES B;DEMIREL BELMA;PEDERSEN PETER S 发明人 YAKOBSON DENNIS L.;CORKADEL CLAUDE C.;BENHAM CHARLES B.;DEMIREL BELMA;PEDERSEN PETER S.
分类号 F02C1/00 主分类号 F02C1/00