发明名称 |
ENTRANCE FOR ARRIVAL OF JACKING PIPE, STRUCTURE OF ENTRANCE FOR ARRIVAL, AND WATER CUT-OFF CONSTRUCTION METHOD FOR ENTRANCE FOR ARRIVAL |
摘要 |
PROBLEM TO BE SOLVED: To securely perform water cut-off handling in an arrival pit mouth of a jacking pipe and recover a drilling machine very safely. SOLUTION: The entrance for arrival composed of an entrance pipe 3 formed to have bore for storing the drilling machine 6 and the jacking pipe 7, a stuffing member 4 attached to a mouth of the entrance pipe 3, and a filling pipe 5 buried in the direction of diameter of the entrance pipe in the stuffing member 4 is attached to the arrival pit mouth 2 of the jacking pipe 7. After the drilling machine 6 and the jacking pipe 7 cut the stuffing member 4 and the filling pipe 5 and arrive in the entrance pipe 3, a grouting material 8 for water cut-off is poured between the entrance pipe 3 and the jacking pipe 7 from the filling pipe 5. COPYRIGHT: (C)2007,JPO&INPIT
|
申请公布号 |
JP2007023546(A) |
申请公布日期 |
2007.02.01 |
申请号 |
JP20050204534 |
申请日期 |
2005.07.13 |
申请人 |
KAJIMA CORP;TAISEI CORP;TEKKEN CONSTR CO LTD;KOMATSU UNDERGROUND MACHINERY LTD |
发明人 |
SHIRAI SHUNSUKE;KAMIO MASAHIRO;YOSHIKAWA TADASHI;HAYASHI NOBORU;IWASHITA ZENICHIRO;MIMURO KEIJI;ANDO TETSUTO;OGAWA FUSHI;MATSUI KENJI;EBARA HIROSHI;YAMAMOTO YOSHIHISA;SAITO HIROYUKI |
分类号 |
E21D9/06 |
主分类号 |
E21D9/06 |
代理机构 |
|
代理人 |
|
主权项 |
|
地址 |
|