发明名称 IMPROVED GROUND CONCURRENTLY USING DIFFERENT TYPES OF SAND COMPACTION PILES (SCP)
摘要 PROBLEM TO BE SOLVED: To provide low-replacement improved ground using steel slag. SOLUTION: In a ground improving structure using the steel slag, a pile 1 made of an unhardenable material such as natural sand, and a steel slag pile 3 are concurrently used in a juxtaposed manner. In the improved ground concurrently using different types of SCP (sand compaction piles), an upper layer section 7 of the improved ground 6 is the improved ground 6 using the piles 1 and 3, and a lower layer section 8 thereof is the improved ground 6 using the pile 1. COPYRIGHT: (C)2007,JPO&INPIT
申请公布号 JP2006348466(A) 申请公布日期 2006.12.28
申请号 JP20050171972 申请日期 2005.06.13
申请人 NIPPON STEEL CORP 发明人 SHINOZAKI HARUHIKO;NAKAGAWA MASAO;KISO EIJI
分类号 E02D3/10;E02D3/08 主分类号 E02D3/10
代理机构 代理人
主权项
地址