摘要 |
PROBLEM TO BE SOLVED: To provide a concrete L type pile capable of shortening a long construction period of time at a low cost since a retaining wall method and a wooden pile method for earth retaining are branch work in a landslide construction site. SOLUTION: A fall of a concrete pile can be prevented by making the concrete pile as an L-shape to enable it to resist tensile load by a cross and uneven shape. Mass production of the concrete L-type pile can be made at a low cost by plant manufacture. A construction period of time can be reduced in the construction site, and design dimensions can be changed in accordance with the site. It is also applicable to emergency repair work. COPYRIGHT: (C)2007,JPO&INPIT
|