PROBLEM TO BE SOLVED: To provide a temporary column structure which enables safe and easy setting and removal of temporary columns when the temporary columns are erected in a building, and to provide a building unit with the temporary columns, and a method of constructing a unit building. SOLUTION: The temporary columns 11 are erected in the building, and each consist of an upper column 53 connected to a ceiling beam 3, a lower column 52 connected to a floor beam 2, and a wedge member 6. The upper and lower columns 53, 52 are erected coaxially with each other. The upper column 53 has a contact surface which makes contact with the wedge member and is inclined at the same gradient as that of the wedge member 6. The wedge member 6 is pinched between the upper column 53 and the lower column 52, and according to horizontal movement of the wedge member 6, the height of the temporary column 11 is adjusted. COPYRIGHT: (C)2007,JPO&INPIT
|