发明名称 METHOD OF CONSTRUCTING IMPERVIOUS LAYER
摘要 PROBLEM TO BE SOLVED: To reduce the construction cost of an impervious wall for the partition revetment of waste reclaimed land by inserting an auxiliary insertion into a layer of an asphalt mixture in an integrated form. SOLUTION: The method comprises performing an impermeability treatment to ground 1, forming a base mound 3, constructing a revetment 5 on the mound 3 by arranging caissons 6 side by side, embedding an auxiliary insertion 19 in a packed layer 4 to be formed in the bottom of the caissons 6 in an integrated form while retaining the thickness of the impervious material, putting the auxiliary insertion in the asphalt mixture block 8a for the edge of the impermeability membrane material 8 to integrate the insertion with the asphalt mixture and inserting the auxiliary insertion into the remainder of the impervious layer between the caissons while retaining the effective thickness of the impervious material to reduce the amount of the impermeable material used but ensure the impervious performance. COPYRIGHT: (C)2006,JPO&NCIPI
申请公布号 JP2006204965(A) 申请公布日期 2006.08.10
申请号 JP20050016257 申请日期 2005.01.25
申请人 WORLD ENGINEERING KK;NIPPON ROAD CO LTD:THE;TAISEI ROTEC CORP;NIPPON KAIJO KOJI KK 发明人 WAGI TAKATSU;ORIGASA MASAMI;NONODA MITSURU;ITO TAKAHIKO;NAKANO HIROSHI
分类号 B09B1/00;E02B3/12 主分类号 B09B1/00
代理机构 代理人
主权项
地址