摘要 |
<p><P>PROBLEM TO BE SOLVED: To provide a baseless construction method for a buried pipe omitting foundation work, and not needing segmentation of back filling and rolling compaction of back filling material. <P>SOLUTION: In the construction method, trench digging is carried out, and the buried pipe is laid in a trench. It is characterized by that the buried pipe is positioned and installed in a separated state from a trench bottom face, and slurry stabilized treated soil is filled at once in the trench until a whole circumference of the buried pipe is hidden. <P>COPYRIGHT: (C)2006,JPO&NCIPI</p> |