摘要 |
PROBLEM TO BE SOLVED: To provide a vibration control cable setting method for setting a vibration control cable on which a helical rope is wound beforehand, in the construction field. SOLUTION: According to the vibration control cable setting method, the vibration control cable 14 is formed by spirally winding the helical rope 37 on a main cable 35, and the vibration control cable 14 having an SUS band and a cover member 55 mounted thereon, is wound on a drum 12, followed by transporting the vibration control cable 14 wound on the drum 12 to the construction field. In the construction field, after removing the SUS band and the cover member 55, the vibration control cable 14 is set. COPYRIGHT: (C)2006,JPO&NCIPI
|