发明名称 ROAD CONSTRUCTION METHOD NEAR BRIDGE ABUTMENT
摘要 PROBLEM TO BE SOLVED: To provide a road construction method near a bridge abutment capable of absorbing an angle of rotation due to the deflection of a bridge girder with a square hooked connector installed to a joining portion between a floor slab at the bridge beam side and a floor slab at the earthwork side. SOLUTION: A square hooked connector 40 is installed in the joining portion between an extended floor slab 17 at the side of a bridge beam 1 and an auxiliary floor slab 23a at the earthwork 7 side; and plural movement-restricting connectors 30 etc. are installed in the auxiliary floor slabs 23 etc. at the earthwork side thereby permitting the expansion and contraction of the structure. COPYRIGHT: (C)2006,JPO&NCIPI
申请公布号 JP2005315017(A) 申请公布日期 2005.11.10
申请号 JP20040136123 申请日期 2004.04.30
申请人 GAEART TK:KK;OSHIGE TOMOYUKI 发明人 OSHIGE TAKESHI;NOMURA KENJI
分类号 E01C11/02;E01D19/06;(IPC1-7):E01C11/02 主分类号 E01C11/02