<p><P>PROBLEM TO BE SOLVED: To increase the reliability of a water shielding structure constructed integrally with a bulkhead by constructing a water shielding layer at a connection part when a structure such as a caisson is constructed or a sheet pipe is driven in a partition bulkhead in an ocean damping and disposing site for waste. <P>SOLUTION: In this partition bulkhead 5 constructed by arranging caissons 6 and 6a, the side faces of the caissons are formed as recessed parts, a rubber seal material 18 is inserted into a narrow part 12 between the caissons, and the water shielding layer 15 is constructed on the wide part 13 therein. In the water shielding layer, a reinforcement cage 16 is inserted therein, and an asphalt mixture 17 is filled therein. Thus, the water shielding layer can be prevented from being deformed by an external force acting on the caissons. <P>COPYRIGHT: (C)2005,JPO&NCIPI</p> |