发明名称 System and process for job scheduling to minimize construction costs
摘要 Increased efficiency and lower cost job scheduling is provided by a system and method that optimizes for cost instead of makespan, and minimizes fluctuations in resource utilization. A schedule is constructed using a workflow scheduling system that includes a load leveler, a cost minimizer, and a manpower planner. The load leveler minimizes makespan, subject to resource limits, and then lowers the resource limits, repeating the process in order to create a flatter schedule. The cost minimizer generates an initial solution, and then incrementally improves it, using the manpower planner to evaluate the different possible solutions. The manpower planner calculates, for a given schedule, the optimal hire/fire decisions to minimize total cost.
申请公布号 US2005065826(A1) 申请公布日期 2005.03.24
申请号 US20010014919 申请日期 2001.12.11
申请人 BAKER ANDREW B.;GINSBERG MATTHEW L.;SMITH TRISTAN;KEITH DANIEL B.;PARKES ANDREW J.;SMITH BRYAN 发明人 BAKER ANDREW B.;GINSBERG MATTHEW L.;SMITH TRISTAN;KEITH DANIEL B.;PARKES ANDREW J.;SMITH BRYAN
分类号 G06Q10/00;(IPC1-7):G06F17/60 主分类号 G06Q10/00
代理机构 代理人
主权项
地址